HOLYHEAD FOOTBRIDGE RIVER CROSSING
About This Project
CMP were contracted to install rock-socketed piles to support Holyhead footbridge.
Works Description
Phase 1
- Mobilise and position the General Zee jack-up barge
- Drive casing tubes into rock from jack-up barge
- Drill socket through casing tubes and clean out debris
- Install steel reinforcement structures within casing tubes
- Fill casing with concrete
- Install pre-cast concrete crossheads on top of piles
- Place and install pre-cast concrete decking beams
Phase 2
- Continuation of rock-socketed foundation piling works from phase 1 but completed from the shore rather than the jack-up barge
Project
Holyhead Footbridge River Crossing
Location
Holyhead, Isle of Anglesey
Category
Coastal, Marine, Piling, Rock Socketed Pile Installation