CMP worked for the Environment Agency as part of the final Folkestone to Cliff End Flood and Erosion Management Strategy, to Construct new timber groynes at the along the beach to prevent it eroding. CMP installed hundreds of timber piles and planks to construct the timber groynes. This piles were driven into the sand using CMP’s ABI piling rig and vibro hammer.
marine piling, marine construction, diving, cofferdams, jack up
16134
portfolio_page-template-default,single,single-portfolio_page,postid-16134,ajax_fade,page_not_loaded,,side_area_uncovered_from_content,qode-theme-ver-10.1.1,wpb-js-composer js-comp-ver-5.0.1,vc_responsive
 

DYMCHURCH BEACH GROYNES

About This Project

CMP worked for the Environment Agency as part of the final Folkestone to Cliff End Flood and Erosion Management Strategy, to Construct new timber groynes at the along the beach to prevent it eroding.

CMP installed hundreds of timber piles and planks to construct the timber groynes. This piles were driven into the sand using CMP’s ABI piling rig and vibro hammer.

All the timber work was skilfully carried out by CMP operatives who are fully trained to cut and shape timber to suit the requirements on site.

Works Description
  • Installation of timber piles and planks to form the new groynes
  • Removal of the existing deteriorated groynes
  • Excavation and movement of beach materials
  • Involved working between tides on the beach day and night
Project

Dymchurch Groynes

Location

Dymchurch, Kent

Client

Environment Agency

Value

£ 1,000,000