09 Oct NUSTAR Jetty 1 and 2
A refurbishment was required to the existing facility located on the river Thames for the Nustar Terminal. This project involved the following:-
Removal of old fender structures
Installation of new piled Breasting and Mooring Dolphins with all associated deck furniture
Installation of interconnecting walkways
Foundation frames for loading arms
Installation of task lights and Navigation lights.
Utilising both Jack Up barges and floating plant the Piles were successfully installed on time and to budget. CMP Thames’ experienced marine operatives and management team ensured the highest quality was achieved on site, Health and safety of other users and our own workforce was maintained to the highest standard.