Phase 3 of this project involving a quay extension to enable use by bulk cargo vessels. CMP Thames Ltd worked as specialist subcontractor to McLaughlin and Harvey Ltd. CMP Thames have undertaken piling work including the following:-

. Installation of ‘King’ concrete reinforced tubular piles 1220mm DIA 36m long. Interconnected with sheet piles to form the front combi wall along gridline A.

. Installation of 914mm DIA 14long and 14.5m long along gridlines B-E.

.

 